When changing pipe diameters leave soffit to soffit connections
When changing the diameter of pipes in flow move the bottom level up and down instead of the top so the connection between the pipes remains soffit to soffit.
Storage structures now automate the upstream IL of the incoming nodes. This overwrites any designed levels and this cannot be bypassed. Remove this structure so that basins can have stepped incoming ILs.
Change the layer of the text within CAD so that it matches the Manhole Type in Flow. Let us change the layering in CAD so that we can present drawings better.
Charles Blundy
about 1 month ago
in SmartTools
0
📋Registered
When selecting hyperlinks from the plan within Flow, it no longer takes you to the selected information, if you're within a different network. Previously, clicking a hyperlink takes you to the information, regardless of network.
When importing SuDS features (i.e. Porous paving) it imports as a SuDS Underdrain in SmartTools. For some reason, this multiplies so you end up with 20 extra overlapping lines on the same layer. Please stop this happening.
Charles Blundy
about 1 month ago
in SmartTools
0
📋Registered
There should be an option to connect an inspection chamber serving a house or apartment unit directly to the network, with a tie-in to the top (soffit) of the main sewer. The invert levels (ILs) of the proposed inspection chambers, and of the tie-...
Sections should show crossing points between different networks
Sections should show crossing points between different networks for example foul and storm so minimum vertical separation distance can be shown to show compliance with Uisce Éireann Code of Practice.
Currently, to stop a return period (e.g. 1 in 30 year) from running in a simulation, you have to delete it entirely. This is a problem when you're testing different storm scenarios but want to keep the full list of return periods for later — you e...
Producing long sections between selected manholes/nodes
For larger sites, where the drainage will be built in phases it would be helpful if when producing long sections we could determine between which manholes we want long sections produced for instead of the whole site. We currently have to export th...